The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and give a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links under each project to the projects site page for those looking for additional information.


Week of December 28 through Week of January 4

We hope everyone is safe, well, and Covid-free.  Here’s what we’ve been working on this Fall!

Classroom and Technology Upgrades

We have started the renovation work on the Perception Lab in Visual Arts. It is now currently scheduled to being be completed in mid-March. Additionally, we are in the process of designing the renovations to Studio A in the Music Building.

CMFT

The Contractor has finished the majority of their work on the building, and is focusing on completing the work on their punch lists.  We are also finishing upgrades to the building security systems.

Dorms

This past summer, we completed heating and finish upgrades in C-Wing, including renovations to a number of corridor bathrooms. We also replaced the complex’s emergency generator to accommodate future card readers on the exterior entrances into Big Haus, Crossroads, and Farside. The card readers have been delayed due to the current pandemic.  We will be replacing some aged mechanical equipment in Crossroads over the next few weeks.

Renovations to Music & Museum Roofs

The contractor has completed their work on the Museum and has moved quickly with their renovations to the Music building’s roofs. They have completed the majority of roofs on the Music building and will continue to work on the central roof (over the basement corridor), and the roof above the third floor over Winter break (weather permitting).

Upgrades to West 1 and Campus Accessibility

Work has been completed on the majority of the renovations to the West 1, West 2, and Central 3 parking lots, along with site improvements and installation of additional ADA parking spaces around our campus.  The contractor is now completing a number of punch-list items and should be complete with this work before the end of January.