The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and given a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links to each of the projects site pages for those looking for additional information.


Week of February 6 through Week of February 13

We hope everyone is safe, well, and Covid-free.  Here’s what we have been working on this Fall!

Academic Restroom Upgrades

We completed and opened the newly renovated restrooms in both the Natural and Social Science buildings.  We will be renovating other buildings this coming summer. 

Classroom and Technology Upgrades

We under construction on the renovations to Studio A in the Music Building.  Additionally, we are finishing some outstanding items on the new Music Production Suite and exploring modifications to another space in the Music Building.

Exterior Masonry Rehab - CCN, CCS & Museum

The contractor is in the process of closing out up their restoration work on Campus Center North, Campus Center South, and the Museum. 

PAC Accessibility Upgrades

The contractor continues their work on creating a new accessible dressing room and an all-gender restroom in the PAC.  Additionally, we are awaiting new hand-railings that will be installed in the main lobby of the PAC.

PAC Exterior Stair Repairs

The project consists of the four exterior stairs between the Main Plaza and the Performing Arts Center.  Construction has begun with three of the four stairs having been poured.  Work will continue into Spring as we restore the walls around the stairs and add new handrails and new lighting.

Pump House & Backflow Preventor

The project which is located at towards the south end of Lincoln Avenue, is under construction.  The pump house structure is complete, and we are awaiting some additional equipment to arrive.  There should be little disruption to the campus during construction.

Rehab of Dance Building Roof

We are in the process of awarding this project and we anticipate construction to begin Spring 2023.

Rehab of Museum’s Southwest Courtyard

The contractor has completed their repairs to the Museum’s southwest courtyard.  They are addressing a few punch-list items.

Stormwater Management Upgrades

Construction will continue into the Spring semester, with most of the upgrades to the bioswale complete.  The project should have little disruption or impact to the campus operations.

Visual Arts Building Mechanical Upgrades

Construction work began over Winter Break with a large part of the demolition work already completed on the basement level.  Swing spaces were also created to help with the displaced programs, with the old Bookstore being converted into a new darkroom suite along with repurposed spaces in the Library.  Construction work will continue through the Spring.