The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and given a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links to each of the projects site pages for those looking for additional information.


Week of September 19 through Week of September 26

We hope everyone is safe, well, and Covid-free.  Here’s what we have been working on this Summer and into the Fall!

Academic Restroom Upgrades

We are finishing the renovations to the restrooms on the 1st floors of both the Natural and Social Science buildings.  Expect some minor disruption and noise which the work occurs.  We will be renovating other buildings next summer. 

Classroom and Technology Upgrades

We under construction on the renovations to Studio A in the Music Building.  Additionally we are finishing construction on the new Music Production Suite.

CMFT

The Contractor has finished the majority of their work on the building, and is focusing on completing the work on their punch lists.  We are also finishing upgrades to the building security systems.

Exterior Masonry Rehab - CCN, CCS & Museum

The contractor has continued their work over the summer on Campus Center North, Campus Center South, and the Museum.  They are finishing their work up on CCN and CCS, while completing demolition work on the Museum.  Expect some noise and vibrations as they work their way around the building. 

PAC Exterior Stair Repairs

The project consists of the four exterior stairs between the Main Plaza and the Performing Arts Center.  We are currently working on the two south stairs.  Expect some noise and vibrations during demolition.  Work will continue through the Fall and Spring.

Pump House & Backflow Preventor

The project which is located at towards the south end of Lincoln Avenue, is under construction. Their should be little disruption to the campus during construction.

Rehab of Dance Building Roof

We are in the process of  re-bidding this project and we anticipate construction to begin Spring 2023.

Rehab of Museum’s Southwest Courtyard

The contractor will continue with their repairs to the Museum’s southwest courtyard.

Stormwater Management Upgrades

Construction will continue into the Fall semester.  The project should have little disruption or impact to the campus operations.

Visual Arts Building Mechanical Upgrades

We have awarded the construction contractor and are working on creating some swing spaces of the programs on the basement level of the building.  Construction work is scheduled to begin over Winter Break.