Temporary Closure of North Section of Lincoln Avenue

Due to necessary repairs to the High Temperature Hot Water line feeding The Commons, the contractor will need to temporarily close the section of Lincoln Avenue between Cottage Avenue and the north Loop Road.  The contractor will have barricades  and directional signage in place.  Lincoln Avenue will still be open up to the Central 5 parking lot.

To review specifics for this project, please visit our Projects in Construction: Rehabilitate Utilidors HTHW Phase 2 page.

Temporary Closure of Southbound Lane of Lincoln Avenue

Due to construction in the Central 3 parking lot area, the contractor will need to temporarily close a section of the southbound lane of Lincoln Avenue next to the Humanities Building.  The contractor will have flagmen to assist in directing traffic.

To review specifics for this project, please visit our Projects in Construction: Improved Access from our Parking Lots to the Main Plaza and Academic Buildings page.

Temporary Closure of Exterior Ramp at University Police

Due to construction to improve accessibility around our campus, the contractor will need to temporarily close the existing ramp outside on the Lincoln Avenue entrance to University Police to install a new ramp and handrails. The stairs into this entrance will remain open while the works occur.

Work is scheduled to begin on June 25th and be completed by July 15th.

For additional access into University Police, please call (914) 251-6900.

To review specifics for this project, please visit our Projects in Construction: Improved Access from our Parking Lots to the Main Plaza and Academic Buildings page.

Exterior Stairs at PAC to Main Plaza are Closed

Due to the ongoing construction on the exterior stairs from the West 1 and West 2 to the Main Plaza, these stairs will be closed until the project is completed (currently on hold by the State due to Covid-19 related issues). In the interim, please utilize the exterior staircase located across from the West 1 parking lot through the CMFT entry pavilion, or the PAC exterior elevator which can be reached via the PAC underpass or through the CMFT entry pavilion.   Alternatively, the plaza can also be reached via the elevators in the interior of the Music (adjacent to the West 2 parking lot) or CMFT buildings.

To review specifics for this project, please visit our Projects in Design: Repairs to PAC Exterior Stairs page.

West 1 Partially Reopened

As construction continues in West 1, 235 parking spaces in this lot are now available for everyone’s use to help alleviate parking congestion. The contractor has also striped 12 new ADA-compliant parking spaces.

Additionally, a damaged stormwater line running beneath the middle of West 1 has been repaired.  The reopening of West 1 is currently scheduled for the end of July 2020.

To review specifics for this project, please visit our Current Projects page.