Project Updates
The Capital Facilities Planning construction project update page is intended to let you know what projects are under construction around campus and how they may impact our students, faculty, staff, and visitors.
The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and given a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links to each of the projects site pages for those looking for additional information.
Week of November 16 through Week of November 23
We hope everyone is safe, well, enjoyed the summer, and are settling back into to the new school year. Here’s what we have been working on and will be working on over the next few months.
Administration Building Exterior Renovations
Construction will continue over the Summer and will into the Spring semester. The contractor will be completing their roofing work and replacing the exterior windows.
Heating Plant Boiler Upgrades
Contractor has been working all summer, and the 1st new boiler has been delivered and installed. The two new additional boilers have also arrived. They will be completing their work on our main boiler this month. The other two back-up boilers will be completed in January.
Interior Upgrades at Olde Apartment Complex
Construction continued this fall, with minor punch list work remaining.
Rehab of Bookstore
The contractor continued their work over the fall. We’ve had a few delays but will be completed the work this semester.
Site Improvements for Accessibility - Phase 3
Construction work is complete in the East 1A parking lot. Work is currently progressing at the Commons apartment complex. Central 2 and East 2 and 3 parking lots.