Project Updates
The Capital Facilities Planning construction project update page is intended to let you know what projects are under construction around campus and how they may impact our students, faculty, staff, and visitors.
The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and given a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links to each of the projects site pages for those looking for additional information.
Week of August 03 through Week of August 10
We hope everyone is safe, well, and enjoying the summer. Here’s what we have been working on and will be working on over the next few months.
Administration Building Exterior Renovations
Construction will continue over the Summer into the Fall semester. The contractor will be completing their roofing work and replacing the exterior windows.
Heating Plant Boiler Upgrades
Contractor has been working all summer, and the 1st new boiler has been delivered. The two new additional boilers are scheduled to arrive shortly. They will be completing their work this Fall.
Rehab of Bookstore
The contractor continued their work over the summer. We’ve had a few delays but will be completed the work this Fall.
Site Improvements for Accessibility - Phase 3
Construction work is almost complete in the East 1A parking lot. Work is currently progressing at the Commons apartment complex.
Interior Upgrades at Olde Apartment Complex
Construction continued this summer, with a scheduled completion before the start of the Fall semester.