Commons Apartments Complex M-Street Sprinkler Upgrades

Following the success of adding sprinklers to both K & P-Streets, this is the last phase of adding sprinklers to the remaining buildings.

Project Overview

The Phase II residences, also known as “The Commons” or “The New”, is a wood-framed apartment complex located on the northwest side of the campus, built in the early 1980, featuring apartment-style living.  The complex is composed of four buildings, K-Street, M-Street, P-Street, and S-Street.  Following a fire in K-Street, the college began the process of installing new sprinklers in the complex.

Sprinklers have already been installed in both K-Street and P-Street over the last two summers. Installation of sprinklers in this building were part of a final phase for installing sprinklers in the complex. 


Lead Agency:  Dormitory Authority of the State of New York

Design:  Cameron Engineering Associates, P.C.

Contractor:  Niram

Budget:  $1.6 Million