Repairs to PAC Exterior Stairs
Repairs and upgrades to the existing four exterior stairs that lead from the West 1 & 2 parking lots to the Main Plaza, including new steps, handrails, lighting and masonry restoration.
Project Update as of February 17, 2025
Construction is complete. Punchlist work should be wrapping up in the next couple of weeks. We are also looking into some leaks in the surrounding areas.
Project Overview
The existing stone and masonry steps on both the north and south sides of the Performing Arts Center, which lead from the West 1 & 2 parking lots up to the Main Plaza, are in a state of disrepair and are suffering from weather-related deterioration.
This project will address these issues by replacing the existing stairs with new poured concrete steps, new handrails, better lighting, and restoring the surrounding masonry walls.
Timeline: Punchlist
Lead Agency: Campus-Let
Design: Grigg & Davis Engineers PC
Contractor: Nafees Construction Corporation
Budget: $1M