Project Updates
The Capital Facilities Planning construction project update page is intended to let you know what projects are under construction around campus and how they may impact our students, faculty, staff, and visitors.
The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and given a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links to each of the projects site pages for those looking for additional information.
Week of April 1 through Week of April 8
We hope everyone is safe, well, and enjoying the Spring semester. Here’s what we have been working on and will be working on over the next few months.
Academic Restroom Upgrades
We are again under construction on our Phase 2 renovations in the Dance & the Library buildings. We took a break over the Fall semester to limit any noise and disruption. Phase 3 has been awarded and we have started work in the Physical Education building and the lower level of the Main Dining Hall. We are additionally developing the next round of restrooms to be renovated on our campus.
Classroom and Technology Upgrades
We are nearly finished with our renovations to Studio A in the Music Building. Additionally, we finished some outstanding items on the new Music Production Suite and renovated another space on the 3rd floor of the Music Building.
Pump House & Backflow Preventor
The project which is located at the south end of Lincoln Avenue, is in the final stages of construction. The pump house structure is complete, and we are awaiting final commissioning on the new equipment. There should be little disruption to the campus during construction.
Rehab of Dance Building Roof
Work continues over the Spring, weather dependent. We’ve received the new skylight, and the contractor is installing it.
Visual Arts Building Mechanical Upgrades
Construction work was completed over the summer and the building is open for use. A few areas on the lower level will remain off-line as we plan on some changes. The temporary Darkroom will remain over in the old Bookstore space. Phase 2 work is scheduled to begin next summer.