FOUNDATION DRAINAGE & WATERPROOFING / THE NEUBERGER MUSEUM OF ART, VISUAL ARTS, NATURAL SCIENCES
Lead Agency / The State University Construction Fund
Design / San Fanandre Justin Architects
Contractor / MPCC Construction Corp.
Budget / $2 million
Completed June 2009

This project addressed the perimeter foundation waterproofing for the Neuberger Museum, the Visual Arts building and the Natural Science building. The project began on May 19th, 2008 with completion in June 2009.